Power Shut Down Notice By DNH Power Distribution Corporation Ltd.
Dear all,
Your association is in receipt of a Public Notice No.DNH/PDCL/NZ-II/223/2011/689, dated 15/02/16 from DNH Power Distribution Corporation Ltd. The scanned copy of the same is attached herewith.
Vide the said Public Notice, DNHPDCL has informed all the consumers that, the power supply will not be available at mentioned Sub-Stations, time and date as shown in the scheduled table given below.
So, all the colleague industries are hereby requested to go through the Public Notice attached herewith and plan their production accordingly.
Scheduled Table
Date of Power Cut | Day | Time | Taken By | Effected Consumes | Remarks |
18.02.2016 | Thursday | 09.00.Hrs.To18.00 Hrs | PGCIL | 66/11kv Athal S/s66/11kv Masat S/s | 220kv Kala- Kharadpada line stringing work |
20.02.2016 | Saturday | 09.00.Hrs.To18.00 Hrs. | PGCIL | 66/11kv Rakholi S/s Shutdown of 66kv Kharadpada – Rakholi Circuit – I & II | 220kv Kala- Kharadpada line stringing work |
Thanking you,
With regards,
For Silvassa Industries & Manufacturers Association
Narendra Trivedi,
Secretary